Electro mechanical and C&I consultancy for Kaleshwaram Extension Link IV Reach 2 (PS2) MID MANER (AT REACH-2)    Electro mechanical and C&I consultancy for PRRLIS Stage I    Electro mechanical and C&I consultancy for Kaleshwaram Extension Link II Reach 2 (PS2) - Yellampally reservoir to MID Maneru Reservoir   Electro mechanical and C&I consultancy for Kaleshwaram Extension Link II Reach 1 (PS1) - Yellampally reservoir to MID Maneru Reservoir    Electro mechanical and C&I consultancy for PRRLIS Stage IV    JWIL given Electrical work and Fire system work for Tanzania Pkg-1

Working on Handia Barrage Micro Lift Irrigation Project and Hydro-Electric Generation Project.

  • 5 X 5MW Unit, 132/11 kV AIS in Substation in Dewas (Madhya Pradesh)
  • 2.5Ha Chak with total power requirement of 19.89 MW in Culturable Command Area (CCA) of 35000 Ha, out of Gross command Area (GCA) 44558 Ha.
  • Working for M/s Karan Development Services Pvt. Ltd. and LCC Projects Pvt. Ltd. (JV).
  • End client is NVDA.